Oakhill, Corona and Carsdale Integrated Renewal Updates - Beechwood lane closure Sept. 28

Project update: Crews are making excellent progress. The base asphalt has already been paved on Corona and the base asphalt on Oakhill will be completed Monday, Sept. 23 The final paving on Beechwood at Corona and at Oakhill is scheduled for Saturday, Sept. 28. The work will take approximately half a day. One lane of Beechwood will be closed at a time with flagging personnel present to direct traffic. Remediation of driveways and landscaping will be underway over the next few weeks. Oakhill and Corona are anticipated to reopen in mid-October and the landscaping is also expected to be completed by then.