St. Laurent Gas Main Replacement Project – Update for Nov. 21 to Dec. 2

Aecon Utilities continues work on the Enbridge Gas St. Laurent Pipeline Replacement project at multiple locations in Rideau-Rockcliffe, Beacon Hill-Cyrville and Alta Vista. The project is near completion with restoration (resurfacing) for Coventry Road in the coming weeks. More than half of the pipe replacement will be completed by mid-November. Lane reductions and temporary road closures/lane closures, pedestrian and cyclists rerouting will continue as is. To address road conditions, the City and the Councillor's office has asked for more frequent street sweeping. 

  • Cummings Ave. between Ogilvie Road and Cyrville Road, as well as Cummings at Labelle
  • Michael Street from Belfast to Labelle
  • St. Laurent Blvd. between Belfast and Tremblay
  • Ogilvie Road from Cummings Avenue to the St. Laurent Blvd. intersection
  • Coventry Road from St. Laurent Blvd., past the Vanier Parkway towards the RCMP building
  • Belfast between Lagan Way and Michael Street
  • Tremblay Road at Avenue K intersection

The work involves the installation of a new 16-inch gas main. Much of the work is being done overnight from 7 pm to 6 am in order to avoid major traffic implications during peak travel periods.