Montreal Road Revitalization update - May 26, 2023

Photo showing artist rendering of the Montreal Road Revitalization project.

The following work is planned May 29 to June 9:
  • Dupuis and Marier Avenue – Installation of the three-sided triangular sign at Le Carrée is proposed in the next two weeks. The sign will allow posting of events and community notices. Reinstatement of the bike repair station at Marier Avenue (removed during the start of construction) is also scheduled in the next two weeks. (May 29 to June 9)
  • McArthur Avenue/Vanier Parkway Intersection – Asphalt and concrete work is continuing at the intersection, including removal and replacement of the existing paver crosswalks. The work is being undertaken at night given the heavy traffic volumes along the Vanier Parkway. The work is being undertaken to revert the intersection back to pre-detour conditions.
  • Greensway Avenue multi-use path – Grading and basecourse placement for the Greensway Avenue to Vanier Parkway pathway connection is scheduled to start next week. (Week of May 29)
  • Landscaping at various locations – Installation of pavers and delineator tiles is occurring throughout Montreal Road. Other work includes concrete repairs, asphalt key grinding at side streets and planter installations.