Work is scheduled to stop on Montreal Road in the next two weeks, December 5 to 16.
Work is scheduled to stop on Montreal Road in the next two weeks (December 5 to December 16), with the following remaining tasks:
- Lafontaine/Granville/Montreal Road intersection – The intersection is scheduled to be opened this Friday, December 9. Remaining work will be completed this week including asphalt ramping and overhead signage – both of which are required to open the intersection.
- Lafontaine to St. Laurent Boulevard – Crews are continuing installation of demarcation tiles and driveway tie-ins over the next week.
- Side street and intersection work – All barrels along Montreal Road will be removed by end of next week and all side streets will be opened.
- Site Cleanup – Crews have started cleaning up the site for the winter and will continue over the next week or so including removal of all construction equipment, material and debris.
A final weekly update will be sent out once construction is completed for this year.
The Montreal Road Project Team