Project update: The Corona piping is complete and homes have already been connected to the new live watermain. On Oakhill, City Drinking Water staff will complete the watermain connection and KCE will finish the storm sewer installation on the next two weeks. The Carsdale watermain work will start on Tuesday, Sept. 3 and is expected to be completed in the next few weeks. Road grading and asphalt paving on Corona, Oakhill, Carsdale and the laneway will be completed in September. Landscaping will take place in early October.
Road closure extension: Given site conditions and ongoing progress, it is anticipated that asphalt paving will be completed by the end of September. The contractor has requested that the roads remain closed for the first two weeks of October so that they can complete the landscaping efficiently.