Starting the week of October 21, 2024, Hydro Ottawa is conducting maintenance hole upgrades on Provender Avenue. This project has an estimated completion date of November 22, 2024. Overall, this work will include:
- electrical infrastructure upgrades;
- lane reductions; and
- sidewalk closures at site.
There are no scheduled power outages associated with this work at this time. Residents may notice increased construction presence throughout the project, including construction vehicles.
Impacted street: Provender AvenueProject start date: October 21, 2024
Project end date: November 22, 2024
Contractor on site: Teraflex Limited
Impacted residential customers: 30
This work will result in street parking restrictions from 40 to 78 Provender Avenue. Parking and construction signage will be in place starting Oct. 18.